Saturday, December 16, 2006

The Telescope & Reflector Begin to Take Shape

A quick disclaimer before today's post: The SPT is not just the primary mirror, and the collaboration does not consist solely of the reflector assembly team. It may seem that way at the moment (at least to readers of this blog), but that will change rapidly as more members of the team --- and more pieces of the instrument --- show up at the Pole. January will bring lots of new faces and much more emphasis on the receiver (i.e., the part of the telescope that actually detects and records the incoming light). But for now, you're going to keep hearing about the telescope infrastructure and the primary mirror.

OK, now back to the post.

Though it may seem slow, the progress on the telescope infrastructure and primary mirror continues --- pretty much on schedule even. A couple of days ago, the first piece of the telescope lower boom (the structure that extends out from the primary mirror and holds the secondary and receiver) went into place, giving the first hint of the scale and final shape of the telescope.

Telescope with part of lower boom


Meanwhile, the reflector assembly folks have spent the last few days in furious panel-placing and -aligning mode. In fact, we're up to a pace of over 20 panels a day placed and aligned to (we hope) less than 100 microns. If we can keep this up, we'll have all the panels placed a few days before Christmas, at which point we spend a couple of days taking care of some wiring and mechanical details, then it's on to testing the surface. The first big test of how well we managed to align the surface will use a technique called photogrammetry. I'll defer a detailed explanation of this process to a later post; for now, it suffices to know that one takes a bunch of pictures with a specially outfitted camera then hands those pictures to an incredibly expensive piece of software that picks out the locations of hundreds of little reflective targets stuck to the mirror surface (and some bigger targets too) and uses that information to determine the exact shape of the mirror surface. You can see the photogrammetry targets (and the progress we've made laying panels) in the picture below. In this photo, Steve P. is using a feeler gauge (a precision set of metal shims) to check the job that Jeff, Ryan, and I did on the latest set of panels. The large metal bars layed across the middle of the reflector are to give the photogrammetry software a known length scale to work with, the foam pads with pressboard on top allow us to walk across the panels, and the shrouded piece of equipment in the center of the reflector is a theodolite (a surveying instrument we use in panel alignment).

Steve checks the alignment job.